Savills – Performance Auditing with achieved savings

At the time of appointment, The Cube comprised a large, new build, multi-use site located in the centre of Birmingham comprising Restaurants, a Hotel, Residential, Offices, Retail, Spa & Leisure Facilities and an underground Car Park.

Energy & Technical Services was initially appointed by Savills to survey the HVAC system and complete an energy audit with a view to establishing a method of monitoring and measuring energy consumption throughout the building.

The initial survey included possible energy savings initiatives, a full asset list, plant performance, planned preventative maintenance (PPM) review, and an assessment of energy / building compliance. Energy & Technical Services were then employed to act as the Energy Managers to complete quarterly energy audits over a three-year period.

Challenge

The building comprises a total floor space of c.450,000 sqft, with multi-use tenancies, which all have different energy requirements. Careful consideration was required for any energy saving initiatives proposed. Solutions needed to remain low cost and also reflect the energy consumption requirements for the various tenancies within this complex multi-use site.

Added Value / Achievements

During the first three months, Energy & Technical Services achieved a pro-rata £25,000 per annum savings through making operational changes to the plant equipment. Energy & Technical Services also helped the client improve operational behaviour, and managed / maintained operational and energy efficiency whilst the building became more densely populated with new tenants.

Energy Survey & HVAC review completed

a pro-rata £25,000 per annum savings achieved 

related CASE STUDIES

Midcounties Co-Operative – Solar Panel Installation Assessment

This project aimed to understand how solar PV installation will benefit the client long term. We have identified the yield and efficiency of solar PV and what the cost of repurposing a number of solar PV panels that were in storage specifically for Co-op. This developed into a compatibility study for solar panel installation across 44 sites.

Date Palm Developments – Complete Building Solutions

Date Palm Developments (DPD) approached ETS to design, install, and commission a new Building Management System (BMS) for their proposed "Ottons Lab." Given the complex nature of the facility, which specialises in plant cloning, highly detailed designs relating to HVAC controls and operational security were necessary to maintain optimal conditions for both plant growth and occupant comfort in the office areas.

BNP Paribas – Simulated Power Failure

The power test was successful with back-up power supplies, fire alarms, emergency lighting, pedestrian access systems all operating as expected during power failure. All equipment operated correctly and efficiently when power was reinstated.